A-A. Tiimanni tn 2: court approved instalments for 914,22 euros in debt and costs
Narva linn, A-A. Tiimanni tn 2 korteriühistu · 80180921
Participants and roles: applicant – Narva linn, A-A. Tiimanni tn 2 korteriühistu; interested person XX – debtor and party to the agreement; association representative XX
How it started · editorial summary
The association and debtor XX agreed on acknowledgment of debt, inclusion of costs and monthly instalments. The court approved the terms and terminated the case.
The dispute and the court’s decision
The court approved the instalment agreement between the apartment association Narva linn, A-A. Tiimanni tn 2 and debtor XX and terminated the case. The association initially sought principal and continuing late-payment interest; before determination, the participants agreed a smaller debt and payment schedule. The ruling does not set out separate debtor objections to the initial charges.
Under the agreement, XX acknowledged unpaid management expenses and other payments. The agreed obligation also includes 25 euros, half the court fee, 300 euros for legal assistance and 3 euros to obtain evidence. The debtor acknowledged that payment was due, and the association gave additional time for voluntary performance.
The schedule provides for monthly payments. The agreement entitles the association to demand late-payment interest of 0,02% per day on unpaid management expenses and other payments from the agreed date. Breach makes the entire agreed obligation immediately payable.
The court examined the documents, checked the agreement’s permissibility and enforceability, approved it on 9 July 2021 and terminated proceedings. Each participant bears expenses not included in the agreement. The court ordered the association refunded 25 euros, half the court fee, from the state budget. The participants waived appeal against the ruling; it does not confirm subsequent payment under the schedule.
Outcome of this decision
Approve monthly instalments for the debt and costs: 25 euros, half the court fee, 300 euros for legal assistance and 3 euros to obtain evidence. Provide for late-payment interest of 0,02% per day on unpaid management expenses and other payments from the agreed date and immediate full payment on breach. Terminate proceedings, leave other costs with the participants and refund the association 25 euros in court fees.
Translation of an anonymised, abridged excerpt from Estonian
II. Terminate proceedings in civil case 2-21-4758 following approval of the settlement.