Kangelaste 44: contractor must reimburse correction of roof defects
Korteriühistu KANGELASTE 44; Narva linn, Kangelaste prospekt 44 korteriühistu · Osaühing IMHOTEPKOMP · 80146002 · 11482887
Participants and roles: Claimant – Korteriühistu KANGELASTE 44; Defendant and appellant – Osaühing IMHOTEPKOMP
How it started · editorial summary
After the contractor’s failed repair, the association engaged another contractor and sought reimbursement.
The dispute and the court’s decision
The circuit court upheld the award of 1 500 euros against Osaühing IMHOTEPKOMP in favour of the apartment association KANGELASTE 44 for remedying roof defects, changing the reasons in part. Korteriühistu KANGELASTE 44 sought 1 500 euros in damages from Osaühing IMHOTEPKOMP after replacement of 17 roof ventilation pipes. The association alleged that the contractor damaged roofing around the pipes, causing leaks, and attempted repairs with bitumen mastic did not cure the defects. Another company was engaged for repairs and a building audit commissioned. The contractor argued that it was not given sufficient time or opportunity to remedy the work and that the expenses were excessive.
The county court granted the claim. Tartu Ringkonnakohus upheld the 1 500-euro award, clarifying its legal reasoning and assessment of the amount. Expert materials and witness testimony supported defects in both the original work and attempted repair. Failed remedial work was a fundamental breach of contract. The association therefore did not have to give the contractor yet another additional deadline and could engage another contractor to remedy the defects.
The circuit court found 1 143,84 euros for remedial work and 360 euros for the audit justified. The total established was 1 503,84 euros, but the association sought only 1 500 euros and that was awarded. Another company’s later, cheaper estimate did not prove the actual cost of the relevant repairs.
Appeal costs were imposed on IMHOTEPKOMP; the county court will quantify them after the judgment becomes final. The judgment confirms the contractor’s compensation obligation, rather than an actual payment to the association.
Outcome of this decision
Dismiss IMHOTEPKOMP’s appeal and uphold the association’s 1 500-euro award. Amend the reasoning in part. The contractor bears appeal costs, to be quantified separately.
Translation of an anonymised, abridged excerpt from Estonian
1. Dismiss the appeal and leave the Viru Maakohus judgment of 11 March 2019 unchanged. Amend the county court judgment’s reasoning in part.